Time & Work-Q114

  • Remaining Timing :-

(1). An engineer wants to completely build a bridge in 90 days and 120 men were set to work, each working 7 hours a day. After 75 days 5/9 of the work is finished. How many extra men may be employed so that the work may be completed in time, each man now working 10 hours a day?

  • (a). 336
  • (b). 216
  • (c). 126
  • (d). 60
  • (e). None of these
Answer : 216

Explanation: